Posted Date: 11/09/2017
Drone Footage of Bonham High School Concrete Pour after 10-26-17 . . .
Posted Date: 10/20/2017
Aerial views of the progress on the new Bonham High School! . . .
Posted Date: 10/20/2017
Slab for flooring in locker rooms/storm shelter was poured and finished on October 12th. Once cured in about 14 days, steel will be erected and the vertical structure will begin. . . .
Posted Date: 10/06/2017
BHS Visual Construction Update; 10-6-2017 . . .
Posted Date: 09/29/2017
The decking is being laid and concrete for the slab will follow in the next week. Grade beams for the southern portion of the building are poured and steel will follow. . . .