Posted Date: 09/13/2017
See attached photos of: Steel is in place on grade beams in the new locker room/storm shelter area. Grade beam concrete pour from pump truck. . . .
Posted Date: 08/31/2017
Grade beams concrete pours, and auger-cast pier drilling. . . .
Posted Date: 08/28/2017
Wind screen installed on fences at student walkway. Wooden walkway being built by carpenters to keep students from walking in mud. . . .
Posted Date: 08/18/2017
After being delayed by the rain this week, the workers are back to the construction site doing work. . . .