BONHAM ISD AGRICULTURAL PROJECT CENTER-CONSTRUCTION UPDATE 9/30/2016

  • The underground utilities on-site and off-site are completed.  All of the earthwork is completed.  

  • We are scheduled to have the foundation completed Friday 9/30/2016.  Masonry is scheduled to start 10/4/16.

  • Perimeter road around the building is scheduled to start 10/3/16.  

  • The metal building materials are all at the manufacturer with 85% of the fabrication completed.

  • Delivery of the metal building is scheduled for 10/10/16 with building erection beginning on 10/17/16.

  • Project is on schedule