Posted Date: 10/20/2017
Slab for flooring in locker rooms/storm shelter was poured and finished on October 12th. Once cured in about 14 days, steel will be erected and the vertical structure will begin.
Posted Date: 10/06/2017
BHS Visual Construction Update; 10-6-2017
Posted Date: 09/29/2017
The decking is being laid and concrete for the slab will follow in the next week. Grade beams for the southern portion of the building are poured and steel will follow.
Posted Date: 09/13/2017
See attached photos of: Steel is in place on grade beams in the new locker room/storm shelter area. Grade beam concrete pour from pump truck.